Chalford Viaduct – Rock Bolting & Netting

Chalford Viaduct – Rock Bolting & Netting
Back to Case Studies

Working with AMCO for 8 months in Stroud

Following a major rockfall at Chalford Viaduct, CAN delivered emergency stabilisation works to make the slope safe and protect the railway below. The initial response led to a wider programme of permanent rockfall protection across the remaining embankment.

CAN Geotechnical was appointed as a subcontractor after a catastrophic failure event.  It was, in fact, approximately 50 m3 of rock, which also led to a large (roughly 3-4 tonne) boulder landing in the four feet of the running line at the toe of the slope.

CAN attended site immediately and escorted a geotechnical engineer onto the site.  An inspection was carried out of the slope to formulate a stabilisation solution.  A week after the inspection, CAN mobilised to site on 16 Jan 2017.

CAN Geotechnical installed a line of top bolts and a temporary rockfall netting drape over the area where the main failure had taken place.  This allowed for a safe installation of the permanent design to take place, and temporary protection for the track below.

High tensile netting system at Chalford Viaduct.

A total of 51 rock bolts were installed in the immediately failed area, overlain with TECCO G65/4 with extra face cables to help the mesh conform to the contours of the slope.  Additionally, Hydroseeded hessian matting was added to further help with the process.

Following the stabilisation of the rock face, CAN broke up the large blocks of rock at the toe and removed them from site, along with any other rocks and debris along the whole length of the catch ditch.  The existing catch fence at the toe was also reinstated.

Following the successful construction of the failure area, CAN was then instructed to stabilise the rest of the embankment.

This included over 200 additional rock bolts, up to 12m in length, and an additional 1800 m2 of TECCO G65/4.

Due to the fractured and voided nature of the limestone, CAN Geotechnical utilised mist flush techniques and grout socks.  This was in order to produce a clean hole and prevent the grout from migrating too far away from the hole.

Trusted by 1200+ companies around the world

Secret Link