CAN was contracted to undertake external building safety inspections across 19 blocks in Enfield, North London.

Using rope access techniques, CAN operatives conducted visual defect surveys and hammer sounding tests to the brickwork & concrete to the external façade of all 19 high rise blocks.

The type, location and size of all defects were recorded on elevation drawings, with photographs to detail the extent of the cracks to brickwork and spalling of the mortar and concrete.

Inspections and reports were completed within the agreed schedule, CAN have since been awarded works for phase 3 of the inspections in Enfield.

Duration:       10 Weeks

Client:            Capital Property & Construction Consultants Ltd

Location:       Enfield, London